Earned Value Management (EVM) can be used to control cost and
measure project performance. Explain the important values
calculated in EVM and how each is interpreted?

Answers

Answer 1

Earned Value Management (EVM) is a project management technique that helps in measuring project performance and controlling costs.

It involves the calculation of several key values that provide insights into the project's progress and financial health. The important values calculated in EVM are: Planned Value (PV): PV represents the authorized budget allocated for the work scheduled to be completed at a specific point in time. It indicates the planned cost for the work performed.

Earned Value (EV): EV represents the value of the work actually completed and approved as per the project plan. It measures the actual progress and accomplishment of the project tasks. Actual Cost (AC): AC represents the total cost incurred for the work performed up to a given period. It includes all direct and indirect costs associated with the project.

Interpreting these values: Cost Variance (CV): CV is calculated by subtracting the AC from the EV. A positive CV indicates that the project is under budget, while a negative CV suggests cost overruns.

Schedule Variance (SV): SV is calculated by subtracting the PV from the EV. A positive SV indicates that the project is ahead of schedule, while a negative SV indicates delays in the project timeline.

Cost Performance Index (CPI): CPI is calculated by dividing the EV by the AC. It indicates the efficiency of cost utilization. A CPI value greater than 1 suggests cost efficiency, while a value below 1 indicates cost overruns.

Schedule Performance Index (SPI): SPI is calculated by dividing the EV by the PV. It indicates the efficiency of schedule utilization. An SPI value greater than 1 suggests the project is ahead of schedule, while a value below 1 indicates schedule delays.

By interpreting these values, project managers can assess the project's cost and schedule performance, identify any deviations from the plan, and take appropriate corrective actions to ensure project success.

Learn more about project here

https://brainly.com/question/28466303

#SPJ11


Related Questions

planners charge a fee that is reduced by the amount of the commissions they earn. a) fee-only b) fee-and-commission c) fee-offset d) commission-based

Answers

Planners charge a c) fee-offset that is reduced by the amount of the commissions they earn.

What is a fee - offset ?

Fee-offset refers to a compensation model where financial planners charge a fee for their services, but the fee is reduced by the amount of commissions they earn from products or services recommended or sold to the client. In this model, the planner's fee is offset by the commissions earned, reducing the overall cost to the client.

In a commission-based model, planners receive compensation solely through commissions earned from the sale of financial products or services, without charging a separate fee.

Find out more on fee - offset at https://brainly.com/question/29430892

#SPJ4

NorthSouth Airlines has been granted permission to fly passengers between major U.S. cities. The new company faces competition from four airlines that operate between the major cities. The betas of the equity of the four major competitors (A, B, C, D) are 2.32, 2.61, 2.82, and 3.11; and the debt-to-equity ratios of these four companies (in the same order A, B, C, D) are 0.23, 0.43, 0.58, and 0.78. Although these D/E ratios vary, all airline debt is rated the same. Suppose the yield on airline debt is 7.0%, the risk-free rate is 3.0% and the expected market risk premium (the average difference between the market return and the risk-free rate) is 7.0%. What is the cost of capital (or discount rate) in percentage that you should use in valuing NorthSouth Airlines? (Allow two decimals in the percentage but do not enter the % sign.)

Answers

The discount rate (or cost of capital) that should be used in valuing NorthSouth Airlines is 16.38%.

We can use the weighted average cost of capital (WACC) formula to calculate the discount rate for NorthSouth Airlines:

WACC = E/(E+D) * Re + D/(E+D) * Rd * (1 - Tc)

Where:

E = market value of the firm's equity

D = market value of the firm's debt

Re = cost of equity

Rd = cost of debt

Tc = corporate tax rate

To calculate the WACC for NorthSouth Airlines, we need to determine the market values of its equity and debt. Since the company is a new entrant, we don't have this information. Therefore, we will assume that the market values of equity and debt are equal, and use the debt-to-equity ratio of 1:1.

So, E/D = 1/1 = 1, which means E = D

The beta for North South Airlines is not given in the question. We can estimate it by taking the average beta of the competitors, weighted by their market values:

Beta_NS = (wA * Beta_A + wB * Beta_B + wC * Beta_C + wD * Beta_D) / (wA + wB + wC + wD)

where wA, wB, wC, wD are the weights of the respective companies in the market.

Assuming that NorthSouth Airlines has an equal market share with each of its competitors, the weights will be equal (i.e. 1/5 each). So,

Beta_NS = (2.32/5 + 2.61/5 + 2.82/5 + 3.11/5) = 2.77

Next, we need to calculate the cost of equity, Re. We can use the Capital Asset Pricing Model (CAPM) to do this:

Re = Rf + Beta_NS * (Rm - Rf)

where Rf is the risk-free rate, Rm is the expected market return, and (Rm - Rf) is the equity risk premium.

Plugging in the given values, we get:

Re = 0.03 + 2.77 * 0.07 = 0.2569 or 25.69%

The cost of debt, Rd, is given as 7.0%.

Assuming a corporate tax rate of 21%, we can calculate the WACC for NorthSouth Airlines:

WACC = (1/2) * 0.2569 + (1/2) * 0.07 * (1 - 0.21) = 0.1638 or 16.38%

Therefore, the discount rate (or cost of capital) that should be used in valuing NorthSouth Airlines is 16.38%.

Learn more about discount rate here

https://brainly.com/question/9841818

#SPJ11

explain strategies campaigns use to win elections. why might digital media be more effective than television ads?

Answers

One of the strategies that campaigns use to win elections is by convincing voters that they are the best choice. This can be done through a variety of ways, such as door-to-door canvassing, rallies, television ads, and digital media.

In recent years, digital media has become an increasingly popular and effective way to reach voters. This is because it allows campaigns to target specific groups of people, and to engage with them directly through social media platforms. Digital media can also be less expensive than television ads, which can be cost-prohibitive for some campaigns.

Additionally, digital media allows for more interactive and engaging content, such as videos and graphics, which can be shared and spread more easily than traditional television ads. Overall, the use of digital media in campaigns has become an essential tool for winning elections, as it allows campaigns to reach voters in a more targeted, cost-effective, and engaging way.

To know more about campaigns visit:-

https://brainly.com/question/30875746

#SPJ11

Problem TWO CAPM (Capital Asset Pricing Model) Using the following information: TRF = 4.7500% rm = 15.5000% bstock = .875000 CALCULATE: Required Rate of Return ANSWER QUESTION: IF the Expected RATE of RETURN = 16.7550%% Is the stock UNDER-valued or OVER valued?

Answers

CAPM (Capital Asset Pricing Model) : The Required Rate of Return is 19.7625%. The stock is UNDER-valued.

To calculate the Required Rate of Return using the Capital Asset Pricing Model (CAPM), we use the formula:

Required Rate of Return = Risk-Free Rate + Beta × (Market Return - Risk-Free Rate)

Given the information provided:

Risk-Free Rate (TRF) = 4.7500%

Market Return (rm) = 15.5000%

Beta (bstock) = 0.875000

Substituting the values into the formula:

Required Rate of Return = 4.7500% + 0.875000 × (15.5000% - 4.7500%)

Required Rate of Return = 4.7500% + 0.875000 × 10.7500%

Required Rate of Return = 4.7500% + 9.406250%

Required Rate of Return = 14.156250%

The expected rate of return is given as 16.7550%. Since the Required Rate of Return (14.156250%) is lower than the expected rate of return, the stock is considered UNDER-valued. This suggests that the stock has the potential to generate higher returns than the required rate of return, making it an attractive investment opportunity.

To know more about  CAPM (Capital Asset Pricing Model), refer here:

https://brainly.com/question/31599998#

#SPJ11

THREE (3) Short Answers and ONE (1) Essay Question Why is the executive summary often categorized as the most important part of a business plan?

Answers

An executive summary is categorized as the most important part of a business plan. This is because it serves as an overview of the entire business plan and captures the reader's attention.

The summary includes the business plan's objectives, the target market, the marketing plan, the business strategy, and the management team's qualifications. Additionally, the executive summary communicates the plan's purpose to prospective investors and stakeholders.

The significance of the executive summary can be further explored in the following ways:

It's a part of the business plan that investors and other stakeholders read first. A well-written executive summary can persuade investors to read the rest of the business plan.It is concise and to the point. The summary captures the plan's core points in a few pages, making it easier to read than the entire plan.It highlights the most critical elements of the business plan. The summary communicates the plan's purpose and the market opportunity, highlighting the most critical elements of the plan. It also provides a synopsis of the business plan in one page.

To know more about executive summary, visit:

https://brainly.com/question/13266012#

#SPJ11

What were the benefits of the green revolution in India?
a. Due to farmers' prolonged and excessive use of synthetic fertilizers, their supply could not match their growing demand. b. While production increased sharply for staple crops, less-favored crops were confined to small-scale production. c. The high costs of pesticides, equipment, and seeds forced farmers to borrow large sums at high interest rates from banks and moneylenders. d. The strain on the treasury caused by the high subsidization of pesticides, equipment, and seeds forced a change in policy.

Answers

The benefits of the Green Revolution in India were primarily centered around the significant increase in agricultural production and food security. The correct answer is option a. Due to farmers' prolonged and excessive use of synthetic fertilizers, their supply could not match their growing demand.

During the Green Revolution, the adoption of modern agricultural practices, including the use of high-yielding varieties of seeds, irrigation, and synthetic fertilizers, led to a substantial increase in crop yields, particularly for staple crops like wheat and rice. This helped meet the growing demand for food and alleviate the problem of food scarcity in India.

The increased agricultural production also had positive socio-economic impacts, such as higher farm incomes, improved rural livelihoods, and reduced dependence on food imports. Additionally, the Green Revolution played a crucial role in reducing poverty and hunger by increasing the availability of affordable food for the population.

While there were challenges and drawbacks associated with the Green Revolution, such as the focus on specific crops and the environmental impact of intensive farming practices, the overall benefits in terms of increased agricultural productivity and food security were significant for India.

learn more about "fertilizers":- https://brainly.com/question/24544067

#SPJ11

Cloud Shoes manufactures recovery sandals and is planning on producing 12,000 units in March and 11,500 in April. Each sandal requires 1.2 yards of material, which costs $3.00 per yard. The company's

Answers

The budgeted cost of purchases for March is $43,200.

Calculation of production requirements: In March, Cloud Shoes plans to produce 12,000 units. Each unit requires 1.2 yards of material, therefore, 12,000 units will require:12,000 x 1.2 = 14,400 yards of material Calculation of material needs: For the production of 12,000 units in March, 14,400 yards of material are required. To meet the policy of having enough material on hand to equal 15% of next month’s production needs, the company will need:15% x 11,500 units = 1,725 units1,725 units x 1.2 yards/unit = 2,070 yards To determine the total material needs for March:14,400 yards + 2,070 yards = 16,470 yards Calculation of cost of purchases: The cost of material per yard is $3.00Therefore, the total cost of purchasing 16,470 yards is:16,470 yards x $3.00/yard = $49,410 To determine the budgeted cost of purchases for March, we need to subtract the cost of material required to meet next month’s production needs: ($49,410) - ($2,070 x $3.00) = $43,200. Therefore, the budgeted cost of purchases for March is $43,200.

Learn more about Budgeted cost: https://brainly.com/question/30506009

#SPJ11

You are part of a software services organization. A new project has been initiated by your sponsor, and you are now authorized as a part of the project management team. The project involves developing a telecommunication application that supports billing. The external customer is the end-user to whom you will deliver the application. As part of the planning, you must develop a comprehensive project plan highlighting all the steps that will be required to support the customer’s request. You must ensure that your plan is professional, concise, and incorporates all the project management guidelines as outlined in each week’s learning. This plan must meet all the criteria of a successful case study project utilizing the steps in the requirements below.

Answers

The comprehensive project plan for the telecommunication billing application will incorporate all necessary steps and adhere to project management guidelines, ensuring a successful case study project.

The project plan will begin with a thorough understanding of the customer's requirements and objectives. It will outline the key deliverables, such as the development of the telecommunication application, ensuring it supports billing functionalities effectively. The plan will include the creation of a project team, assigning roles and responsibilities, and establishing clear communication channels. It will incorporate a detailed timeline, breaking down the project into manageable phases and milestones. Additionally, the plan will encompass resource allocation, budgeting, risk management, and quality assurance measures. Regular progress monitoring, reporting, and stakeholder engagement will be integral parts of the plan. By following these steps and guidelines, the project team will ensure a professional, concise, and successful case study project that meets the customer's requirements.

To know more about , project team , click here https://brainly.com/question/31682184

#SPJ11

The Avis Company is a car rental company and is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 3 minutes. The average traveling time (a round trip) is 21 minutes. a. Apply Little's Law in this case, how many Avis buses are traveling to and from the airport? (Round your answer to the nearest whole number. Enter the numbers only the following blank)

Answers

According to Little's Law, there are approximately 7 Avis buses traveling to and from the airport.

Explanation: Little's Law states that the average number of customers in a stable system is equal to the average arrival rate multiplied by the average time a customer spends in the system. In this case, we can apply Little's Law to calculate the number of buses:

The average number of buses = (Average arrival rate) x (Average time for a round trip)

The average arrival rate can be calculated by dividing the number of buses dispatched per minute by the time for a round trip:

Average arrival rate = (1 bus dispatched every 3 minutes) / (21 minutes for a round trip)

Calculating the above, we get:

Average arrival rate = 1/3

Now, we can calculate the average number of buses:

Average number of buses = (1/3) x (21 minutes) = 7

Therefore, according to Little's Law, there are approximately 7 Avis buses traveling to and from the airport.

learn more about arrival rate here:

https://brainly.com/question/17063529

#SPJ11

XYZ Corp. had established a production plant in Thailand. Recently it decided to close the plant and move production to Mexico. This decision was likely made after XYZ estimated total landed cost of two alternative offshoring options. This statement is T OR F?

Answers

The given statement, "XYZ Corp. had established a production plant in Thailand. Recently it decided to close the plant and move production to Mexico. This decision was likely made after XYZ estimated the total landed cost of two alternative offshoring options" which is likely to be true.

Landed costs refer to the total cost of a product when it arrives at a buyer's doorstep. The amount paid for shipping and handling, customs duty, insurance, and any other charges incurred while transporting the product is included in the total landed cost.

Therefore, by estimating the total landed cost of two alternative offshoring options, XYZ Corp. decided to move the production plant from Thailand to Mexico. The estimation of the total landed cost could have helped the company determine which location would be more cost-effective.

To know more about the Offshoring visit:

https://brainly.com/question/30320636

#SPJ11

If a brand finds a product defect, they should try to keep conversation about it quiet.

a. true
b. false

Answers

The statement "If a brand finds a product defect, they should try to keep conversation about it quiet" is FALSE. Brands should not keep quiet about product defects. Why should a brand not keep quiet about product defects? In today's digital age.

social media and product review websites have given consumers more power to express their opinions and experiences. It is simple for customers to express their opinions about products online and have a significant impact on how other potential buyers view the product. The advantages of disclosing defects in your products include: Better Business.

Reputation: A business that takes responsibility for its mistakes and demonstrates a willingness to resolve problems has a better reputation with its customers. More Trust: When a business openly acknowledges its product flaws, it can boost consumer trust and loyalty. If a business appears to be covering up or concealing its flaws, it loses consumer trust and goodwill. Increasing the likelihood of future purchases: Finally, when a business is open and honest about product defects, it can inspire customer confidence and commitment. This increased trust and commitment to your brand may encourage customers to return in the future for additional purchases.

To know more about product visit:

https://brainly.com/question/31815585

#SPJ11

the following ad appeared in the Imperial Valley Press: For Sale: Stolen black diamond earrings, rare, beautiful, retail value: $600, Asking price is $10. First come, first served. Contact Tate at 555-5599. Kate was the first to contact Tate, and show up to buy the earrings. Kate tendered $10 to Tate, who gave her the earrings. Is there an enforceable contract between Tate and Kate? Fully explain your decision, and your reasoning.

Answers

In this scenario, there is no enforceable contract between Tate and Kate. A contract requires mutual assent, consideration, capacity, and legality of object.

The sale of stolen property is illegal, therefore, the contract cannot be enforced by law. Therefore, Kate cannot be forced to return the earrings.Here's why:For a contract to be enforceable, the object of the contract must be legal. In this case, Tate is attempting to sell stolen black diamond earrings.

The sale of stolen property is illegal, therefore, the contract between Tate and Kate is not enforceable.Therefore, there is no enforceable contract between Tate and Kate. The sale of stolen property is illegal, therefore, the contract cannot be enforced by law. Therefore, Kate cannot be forced to return the earrings.Here's why:For a contract to be enforceable, the object of the contract must be legal. In this case, Tate is attempting to sell stolen black diamond earrings.

To konw more about legality visit:

https://brainly.com/question/31302898

#SPJ11

Use Improvement tools (Poke-Yoke, Simulations, Mistake-Proofing, Spaghetti Diagrams) to evaluate improvements, and implement ideas. Submit a file or document with your potential solutions, based on what you have learned about the process.

Answers

Improvement tools such as Poke-Yoke, Simulations, Mistake-Proofing, and Spaghetti Diagrams are vital for evaluating improvements and implementing ideas in various industries. Poke-Yoke is a technique used to prevent mistakes by making it impossible to make an error during the process.

It is designed to detect any mistake that can occur in a process, thereby eliminating it. Simulations are used to identify potential bottlenecks, shortcomings, and limitations in a process. By simulating the process using relevant data, companies can get an accurate picture of the performance of a process and the areas that need improvement. Mistake-proofing is another improvement tool used. Using these improvement tools will provide insights into how a process can be optimized.

By implementing the ideas generated by these tools, companies can improve efficiency, reduce costs, and eliminate errors. It is essential to note that the effectiveness of these tools is dependent on how they are used. As such, companies should seek the services of experts who can help them develop and implement solutions based on the insights generated. In conclusion, the use of improvement tools such as Poke-Yoke, Simulations, Mistake-Proofing, and Spaghetti Diagrams is a critical step towards improving processes.

To know more about Improvement visit:-

https://brainly.com/question/30637765

#SPJ11

"a.) Write a brief explanation of each of the following terms:-
i.) productivity;
ii.) staff authority.
b.) Identify TWO major 'forces' in the general environment (one 'technological'
and one 'demographic') that are having an impact on the employment of people in
work organizations.
c.) Explain ONE of the forces that you identified in b.) above, and why it is creating
a significant challenge for human resource managers."

Answers

They play a crucial role in developing policies and practices that promote responsible and ethical use of technology while fostering employee well-being and engagement in a technology-driven workplace.

a) i) Productivity refers to the efficiency and effectiveness with which inputs (such as labor, capital, and resources) are utilized to produce outputs (goods or services). It measures the output generated per unit of input and is a key factor in determining the efficiency and profitability of an organization.

ii) Staff authority is a type of authority in an organizational hierarchy where individuals have the power to advise, support, and provide recommendations to line managers and employees. Staff authority positions are typically found in functions like human resources, legal, or finance, and they provide specialized expertise and guidance to support the decision-making process.

b) Two major forces in the general environment impacting employment are:

i) Technological force: The rapid advancements in technology, such as automation, artificial intelligence, and digitalization, are transforming the nature of work and the skills required. These technological advancements are reshaping job roles, eliminating some jobs, and creating new ones that demand different skill sets.

ii) Demographic force: The changing demographics of the workforce, including factors like aging populations, generational shifts, and increasing diversity, have significant implications for employment. Different age groups and diverse backgrounds bring varied expectations, preferences, and skill sets, requiring organizations to adapt their strategies to attract, retain, and engage a diverse workforce.

c) One force that is creating a significant challenge for human resource managers is the technological force. The rapid advancements in technology are leading to automation and the adoption of artificial intelligence in various industries. While these technological developments bring efficiency and productivity benefits, they also pose challenges for HR managers.

The integration of technology in work processes may result in job displacement or changes in job requirements. Employees may need to acquire new skills to adapt to technological advancements, leading to the need for reskilling and upskilling initiatives. HR managers must address the challenges of managing a workforce with diverse skill sets, facilitate training programs, and ensure a smooth transition to technology-driven work environments.

learn more about employee here:

https://brainly.com/question/27005523

#SPJ11

Steve Goodman, production foreman for the Florida Gold Fruit Company, estimates that the average sale of oranges is 4,700 and the standard deviation is 500 oranges. Sales follow a normal distribution. • What is the probability that sales will be greater than 5,500 oranges? • What is the probability that sales will be greater than 4,500 oranges? • What is the probability that sales will be less than 4,900 oranges? What is the probability that sales will be less than 4,300 oranges? .

Answers

Given: Steve Goodman, production foreman for the Florida Gold Fruit Company, estimates that the average sale of oranges is 4,700 and the standard deviation is 500 oranges. Sales follow a normal distribution.

To find:• What is the probability that sales will be greater than 5,500 oranges?• What is the probability that sales will be greater than 4,500 oranges?• What is the probability that sales will be less than 4,900 oranges?What is the probability that sales will be less than 4,300 oranges?Formula used:z = (x - μ) / σWhere,μ = meanσ = Standard deviationz = standard scorez score for a value of X is given as z = (X - μ) / σStandard Normal Distribution Table for probability calculations:

Calculation:We know,Mean (μ) = 4,700Standard Deviation (σ) = 500a) The probability that sales will be greater than 5,500 orangesμ = 4700σ = 500X = 5500z = (X - μ) / σ= (5500 - 4700) / 500= 1.6Using the z-table, we find that the area to the right of z=1.6 is 0.0548.So, the probability that sales will be greater than 5,500 oranges is 0.0548. Hence, option A is correct.b) The probability that sales will be greater than 4,500 orangesμ = 4700σ = 500X = 4500z = (X - μ) / σ= (4500 - 4700) / 500= -0.4Using the z-table, we find that the area to the right of z=-0.4 is 0.6554.So, the probability that sales will be greater than 4,500 oranges is 0.6554. Hence, option B is correct.c) The probability that sales will be less than 4,900 orangesμ = 4700σ = 500X = 4900z = (X - μ) / σ= (4900 - 4700) / 500= 0.4Using the z-table, we find that the area to the left of z=0.4 is 0.6554.So, the probability that sales will be less than 4,900 oranges is 0.6554. Hence, option C is correct.d) The probability that sales will be less than 4,300 orangesμ = 4700σ = 500X = 4300z = (X - μ) / σ= (4300 - 4700) / 500= -0.8Using the z-table, we find that the area to the left of z=-0.8 is 0.2119.So, the probability that sales will be less than 4,300 oranges is 0.2119. Hence, option D is correct.

To know more about standard deviation, visit:

https://brainly.com/question/29115611

#SPJ11

Consider the following two mutually exclusive projects: Cash Flow Cash Year (A) Flow (B) 0 $365,000-$40,000 1 $38,000 $20,300 2 $47,000 $15,200 $14,100 3 $62,000 4 $450,000 $11,000 What is the IRR of

Answers

To calculate the internal rate of return (IRR) for each project, use the trial-and-error method or a financial calculator or software. In this case, let's use the trial-and-error method to find the IRR.

For Project A:

IRR(A) = Unknown

For Project B:

IRR(B) = Unknown

To find the IRR, we set the NPV of each project equal to zero and solve for the discount rate (IRR) that makes the equation true. Let's calculate the NPV for each project using the given cash flows and discount rates:

For Project A:

NPV(A) = -$365,000 + $38,000/(1+IRR(A))^1 + $47,000/(1+IRR(A))^2 + $62,000/(1+IRR(A))^3 + $450,000/(1+IRR(A))^4 = 0

For Project B:

NPV(B) = -$40,000 + $20,300/(1+IRR(B))^1 + $15,200/(1+IRR(B))^2 + $14,100/(1+IRR(B))^3 + $11,000/(1+IRR(B))^4 = 0

By solving these equations simultaneously, we can find the IRR for each project.

Using a financial calculator or software, the IRR for Project A is approximately 20.62%.

Using a financial calculator or software, the IRR for Project B is approximately 11.23%.

Therefore, the IRR for Project A is approximately 20.62%, and the IRR for Project B is approximately 11.23%.

To know more about Net Present Value (NPV) visit-

brainly.com/question/29423457

#SPJ11

Puan Endang and Mr Hyder are small entrepreneurs who are in the manufacturing business of processing health products in North Perlis. Their business was registered under the Partnership Act 1961 under the name Endang Hyder Partnership (EHP). In the final quarter of 2021, EHP had a net income of RM80,000. Endang's balance of capital as of 1 October 2021 was RM60,000 and Hyder RM80,000. Meanwhile, there was a drawing of RM10,000 made by Hyder on 31 December 2021. The details of the agreement between them are as follows: 1. Salary of RM4,000 per month is allowed on Endang and RM8,000 per month on Hyder. 2. Interest on authorized capital at the rate of 10% per annum of the initial balance of capital. 3. Profit and loss are divided equally. 4. The partnership uses the fluctuating capital method to account for its equity. Required: Set up for EHP businesses: A. The table of the distribution of profit and loss for the 3 months ended December 31, 2021. B. Closing entry to record profit and loss distribution as of 31 December 2021. C. The Partnership Capital Statement for the 3 months ended 31 December 2021. D. Explain what "unlimited liability" means

Answers

For the Endang Hyder Partnership (EHP) in the final quarter of 2021, the net income was RM80,000. The capital balances as of October 1, 2021, were RM60,000 for Endang and RM80,000 for Hyder. Hyder made a drawing of RM10,000 on December 31, 2021.

The partnership agreement includes a monthly salary of RM4,000 for Endang and RM8,000 for Hyder, interest on authorized capital at a rate of 10% per annum, and an equal division of profit and loss. The partnership uses the fluctuating capital method.

A. To set up the distribution of profit and loss for the 3 months ended December 31, 2021, the net income of RM80,000 will be divided equally between Endang and Hyder, resulting in RM40,000 for each partner.

B. The closing entry to record the profit and loss distribution as of December 31, 2021, will involve debiting the Profit and Loss Distribution account for RM80,000 and crediting the respective capital accounts of Endang and Hyder for RM40,000 each.

C. The Partnership Capital Statement for the 3 months ended December 31, 2021, will show the capital balances of Endang and Hyder at the beginning of the period, any additional investments or drawings made, the allocation of profit or loss, and the closing capital balances.

D. "Unlimited liability" means that the partners of a partnership are personally liable for the debts and obligations of the business. In the event of any financial shortfall or liability of the partnership, the partners are personally responsible for fulfilling those obligations, and their personal assets can be used to satisfy the partnership's debts. This is in contrast to limited liability, where the owners' liability is limited to their investment in the business and their personal assets are protected from the business's obligations.

Learn more about Partnership here: https://brainly.com/question/31218587

#SPJ11

Consider the following information for a closed economy. Symbol Definition Value C1 0.65 Marginal propensity to consume Autonomous consumption CO 370 t₁ Tax rate 0.15 I Investment 700 G Government expenditure 200 Let's denote real GDP and consumer expenditure by Y and C. Assuming that taxes, T, are a fixed proportion of income, you are asked to find: 1. The expression for total demand, Z. (3 points) 2. The equilibrium level of real GDP. (5 points) 3. The equilibrium level of consumer expenditure. (4 points) 4. The equilibrium level of saving. (3 points) 5. The investment multiplier. (3 points) 6. The government's budget deficit, GBD. (3 points) 7. The leakages from and injections into the circular flow of income and expenditure. Do leakages equal injections? (4 points) 8. Without doing any calculation, explain verbally (discuss the transmission mechanisms and use graphs when possible) the impact on the government budget deficit of: (a) an increase in households' autonomous consumption. (5 points) (b) a reduction in the marginal tax rate, t₁

Answers

A reduction in the marginal tax rate, t₁, would increase the proportion of income available for consumption.

1. The expression for total demand, Z:

Total demand (Z) is the sum of consumer expenditure (C), investment (I), and government expenditure (G), minus net taxes (T). Therefore, the expression for total demand is:

Z = C + I + G - T

2. The equilibrium level of real GDP:

In equilibrium, total demand (Z) equals real GDP (Y). Therefore, setting Z equal to Y, we have:

Y = C + I + G - T

3. The equilibrium level of consumer expenditure:

Autonomous consumption (C1) represents the part of consumption that does not depend on income. The equilibrium level of consumer expenditure (C) is given by:

C = C1 + (1 - t₁) × (Y - T)

Here, (1 - t₁) represents the proportion of income available for consumption after taxes.

4. The equilibrium level of saving:

Saving (S) is the difference between income (Y) and consumption (C). Therefore, the equilibrium level of saving is:

S = Y - C

5. The investment multiplier:

The investment multiplier (K) represents the change in equilibrium real GDP (Y) resulting from a change in investment (ΔI). It can be calculated as:

K = 1 / (1 - MPC)

Where MPC is the marginal propensity to consume. In this case, the given MPC is 0.65, so the investment multiplier is approximately 2.86.

6. The government's budget deficit, GBD:

The government's budget deficit (GBD) is the difference between government expenditure (G) and net taxes (T). Since net taxes are calculated as the tax rate (t₁) multiplied by income (Y), the government's budget deficit is:

GBD = G - t₁ × Y

7. The leakages from and injections into the circular flow of income and expenditure:

Leakages from the circular flow of income and expenditure include savings (S) and taxes (T). Injections into the circular flow include investment (I) and government expenditure (G).

Whether leakages equal injections depends on the equilibrium condition. If leakages equal injections (S + T = I + G), the economy is in equilibrium. Otherwise, there is a surplus or a deficit.

8. (a) An increase in households' autonomous consumption:

An increase in households' autonomous consumption (C1) would lead to an increase in consumer expenditure (C) at each level of income. This would increase total demand (Z), resulting in an upward shift of the aggregate demand (AD) curve. In the short run, this could lead to an increase in real GDP (Y) as firms respond to higher demand by producing more output. However, the long-term impact on the government's budget deficit would depend on the effect of increased consumption on tax revenues and any associated changes in government spending.

(b) A reduction in the marginal tax rate, t₁:

A reduction in the marginal tax rate, t₁, would increase the proportion of income available for consumption. This would increase consumer expenditure (C) and total demand (Z), potentially leading to an increase in real GDP (Y) in the short run. However, the impact on the government's budget deficit would depend on the extent to which the reduction in taxes is offset by changes in government spending or other factors affecting tax revenues. A lower tax rate could potentially result in a higher budget deficit if the increase in government spending or decrease in tax revenue exceeds the increase in consumption.

To know more about consumption follow the link:

https://brainly.com/question/30623688

#SPJ11

Specify what type/types of "Discrimination" is/are explained in the case study regarding the formal complaint demonstrating the situation of Belinda the teller-trainee?

Answers

The case study of Belinda the teller-trainee is a typical example of workplace discrimination. Belinda is facing two types of discrimination at her workplace. The first one is racial discrimination, and the second one is gender discrimination. Racial Discrimination The racial discrimination against Belinda is evident in the behavior of her co-worker, John, who makes fun of her heritage.

Belinda is African-American, and John has repeatedly made jokes about fried chicken and watermelon, which are offensive remarks against black people. Such behavior is an indication of racial discrimination that Belinda is facing at the workplace. Gender Discrimination The second type of discrimination that Belinda is experiencing is gender discrimination. She is being given a job title that is gender-biased, and that is not aligned with her job description. Belinda is being called a teller-trainee, while in reality, she is working as a teller.  

This behavior is an indication of gender discrimination. In conclusion, Belinda is facing two types of discrimination at her workplace. She is facing racial discrimination as her co-worker is making fun of her heritage, and gender discrimination, as she is being given a gender-biased job title that is not aligned with her job description. Therefore, Belinda has filed a formal complaint to address the situation.

To know more about workplace visit:-

https://brainly.com/question/19965171

#SPJ11

which intangible product is exchanged directly between the producer and the customer?

Answers

The intangible product which exchanged directly btwn the producer and customer is " service "

Question 7 1 Point A plastic bags factory has controls over the quality of the raw material. This type of control is Feedforward Control as it focuses on preventing anticipated problems since it takes place during the input stage. Feedforward Control as it focuses on preventing anticipated problems since it takes place during the transformation of inputs to outputs stage. Concurrent Control as it focuses on preventing anticipated problems since it takes place during the transformation of inputs to outputs stage. Feedback Control as it focuses on preventing anticipated problems since it takes place after inputs have been transformed into finished outputs.

Answers

A plastic bag factory has controls over the quality of the raw material. This type of control is Feedforward Control as it focuses on preventing anticipated problems since it takes place during the input stage. Thus, option A) is correct.

Feedforward control is a type of control mechanism that occurs before the transformation of inputs into outputs. It aims to prevent problems or deviations from occurring by focusing on the early stages of the process. In the case of the plastic bags factory, having controls over the quality of the raw material is an example of feedforward control.

By implementing quality controls at the input stage, the factory can anticipate and prevent potential issues that may arise during the transformation of the raw material into finished plastic bags. This proactive approach allows the factory to identify and address any quality concerns before they impact the production process or the final product.

Feedforward control is particularly useful in industries where the quality of inputs significantly affects the quality of the output. By ensuring that only high-quality raw materials are used, the factory can minimize defects, rework, and waste, leading to improved efficiency and customer satisfaction.

In conclusion, the controls over the quality of the raw material in the plastic bags factory align with feedforward control since they focus on preventing anticipated problems during the input stage of the production process. Thus, option A) is correct.

To know more about Feedforward Control refer here:

https://brainly.com/question/28060959#

#SPJ11

You are evaluating an investment project, Project VV, with the following cash flows:
Period End-of-period cash flow
0 –$100,000
1 20,000
2 40,000
3 600,000

Calculate the following: (a) Payback period

Answers

To calculate the payback period for the investment project, you need to determine the time it takes for the cumulative cash flows to equal or exceed the initial investment of $100,000.

In this case, the cash flows at the end of each period are as follows:

Period 0: -$100,000

Period 1: $20,000

Period 2: $40,000

Period 3: $600,000

To find the payback period, you start by subtracting the cash flows from the initial investment until the cumulative cash flows become positive or zero.

Payback Period Calculation:

Period 0: -$100,000 - $20,000 = -$120,000

Period 1: -$120,000 - $40,000 = -$160,000

Period 2: -$160,000 + $600,000 = $440,000 (cumulative cash flows become positive)

The payback period is the time it takes to reach or exceed the initial investment, which is at the end of Period 2. Therefore, the payback period for Project VV is 2 years.

Note: The payback period does not take into account the time value of money or consider the cash flows beyond the payback period. It is a simple measure to assess the time required to recover the initial investment.

Learn more about   investment here-

https://brainly.com/question/29547577

#SPJ4

According to the New Keynesian model, an increase in government spending:
Increases output without any effect on price Shifts the long-run supply curve to the right Increases price without any effect on output Increases both output and price

Answers

The statement "Increases both output and price" best captures the effects of an increase in government spending in the New Keynesian model, acknowledging the short-run increase in output and the potential for price increases in both the short and long run.

According to the New Keynesian model, an increase in government spending has the potential to affect both output and price levels in the short run. The New Keynesian model emphasizes the role of nominal rigidities, such as sticky prices, which result in price adjustments being slow and incomplete in the short run.

In the short run, an increase in government spending can lead to an increase in aggregate demand, which stimulates economic activity and can lead to higher output levels. This occurs because the increase in government spending increases total spending in the economy, which in turn boosts production and employment.

However, in the New Keynesian framework, the increase in government spending may also put upward pressure on prices due to the limited ability of firms to adjust prices immediately. As a result, the short-run effect of increased government spending can lead to both higher output and higher prices.

In the long run, however, the New Keynesian model suggests that prices become more flexible, allowing them to adjust fully. In the long run, an increase in government spending is not expected to have a sustained impact on output, but it can lead to higher prices as the economy reaches its potential output level.

Therefore, the statement "Increases both output and price" best captures the effects of an increase in government spending in the New Keynesian model, acknowledging the short-run increase in output and the potential for price increases in both the short and long run.

Know more about Keynesian Model here:

https://brainly.com/question/31538334

#SPJ11

A father wants to gift his daughter a present for her marriage, he offers her three options: Option A: $55,000 today Option B: $8,000 every year for 10 years Option C. $90,000 in 10 years Assuming a discount rate of 7%, calculate the present value of each option (give an answer for each) and decide what option is best for the daughter For the toolbar, press ALT+F10 (PC) or ALT+FN+F10 (Mac). BIUS Paragraph Arial 10pt A IX0

Answers

The father offers his daughter three options for a marriage gift: Option A, a lump sum of $55,000 today; Option B, an annual payment of $8,000 for 10 years; and Option C, a lump sum of $90,000 in 10 years.

To determine the present value of each option, we need to discount the future cash flows to their current value using the discount rate of 7%.

For Option A, the present value is simply the offered amount of $55,000 since it is received immediately.

For Option B, we need to calculate the present value of the annual payments of $8,000 for 10 years. Using the formula for the present value of an ordinary annuity, the calculation yields a present value of approximately $58,574.

For Option C, we need to calculate the present value of the $90,000 to be received in 10 years. Using the formula for the present value of a single future amount, the calculation yields a present value of approximately $51,934.

Comparing the present values, Option B has the highest value of $58,574, followed by Option A with $55,000, and Option C with $51,934. Therefore, Option B, receiving $8,000 annually for 10 years, is the best choice for the daughter based on present value calculations and the given discount rate.

Learn more about payments here:

https://brainly.com/question/8401780

#SPJ11

Scenario: I NEED THOUGHTS AND DETAILED OPINIONS AND A TIMELINE

You are employed by a large community hospital in the finance department in your city. Recently, there has been a system wide restructuring of leadership and several new projects have been developed to improve quality of care and the patient experience. Your department director meets with you to discuss an opportunity for you to lead a team that will look at the low HCAHP scores and poor hospital specific patient survey results the Emergency Department has received over the last year. Leadership wants to review the areas in which the ED has received the lowest scores: Patient-centeredness, safety, and timeliness of care. The goals of the project are to improve the patient experience by creating a patient-centric environment, decrease errors made by ED providers, and decrease ED wait times by at least 50% (the current wait time is an average of 3 hours).

You will be the team leader and will choose your 5 member team. You and your team will then develop the process improvement plan to address these issues. Your director would like you to present your plan to executive leadership in 2 weeks.

Positions- (Front desk staff/nursing station staff, Porter, Nurse/ Floor Manager, Schedular, Financial Analyst, Marketing Personnel, Emergency department resident doctor)

- An overview of the 3 major issues in the Emergency Department identified through HCAHP scores and hospital specific patient surveys

- Team members you have chosen and why you chose them

- What each member's roles and responsibilities will entail (Be specific. Who will you choose from what departments? Why did you choose each person? What characteristics and skill sets are you looking for? Is your team multidisciplinary? Will you choose any team members from outside your organization? Think about who will be the best people to give you clear perspectives and thoughtful solutions)

- What will be your role as team leader?

- How and how often will you communicate with your team?

- What are the steps you and your team will take to develop this process improvement project?

- Your timeline for implementation of your plan

- What are the project's objectives?

You may include any other information you feel is relevant in relaying your vision to hospital leadership, but remember to be specific. You have creative license as to the specific details of your hospital and the specificity of the problems that were identified. Example: you can say the errors being made are related to medication errors, procedural errors, increase in preventable falls, etc.

Answers

The main objective of this project is to identify and reduce the frequency of preventable medical errors in the hospital. These errors can include medication errors, procedural errors, falls, and other types of errors that lead to harm or injury to patients.

The timeline for this project will be determined by the scope of the problem and the resources available to address it. This may involve the implementation of new policies and procedures, staff training, or the use of new technologies or systems to improve patient safety.

It will be important to regularly evaluate the effectiveness of these interventions and make adjustments as needed to continue reducing the rate of preventable errors. In addition to improving patient safety, this project will also help to improve the reputation of the hospital and increase patient satisfaction.

To know more about medical errors, refer to the link:

https://brainly.com/question/31565918#

#SPJ11

An engineer deposits $20,000 in a savings account on her birthday. She deposits an additional $5,000 on every birthday after that. The account earns 7% interest compounded annually. How much money will be in the account at the end of twenty years? a. $283,379 b. $273,982 c. $282,374 d. $200,000

Answers

a) The amount of money in the account at the end of twenty years will be $282,374, where the account earns 7% interest compounded annually.


To calculate this, we use the formula for compound interest: A = P(1 + r/n)^(nt), where A is the future value, P is the principal amount, r is the annual interest rate, n is the compounding period per year, and t is the number of years.
In this case, the initial deposit is $20,000, the annual interest rate is 7% (or 0.07 as a decimal), the compounding period is 1 (compounded annually), and the number of years is 20. Plugging these values into the formula, we get:
A = $20,000(1 + 0.07/1)^(1*20) = $282,374.
Therefore, at the end of twenty years, the account will have a balance of $282,374.

To know more about ,compound interest, click here https://brainly.com/question/30947446

#SPJ11

23. which of the following is not a money market instrument? group of answer choices bankers' acceptance treasury bill commercial paper preferred stock

Answers

Out of the options given, preferred stock is not a money market instrument.What is a money market instrument?A money market instrument is a debt security that matures in less than a year and is generally considered to be a low-risk investment because of its short-term nature and high liquidity. These securities are used by entities to manage short-term funding requirements.

These investments can be issued by various entities, including corporations, governments, and financial institutions.Preferred stock, on the other hand, is a type of stock that pays dividends to shareholders. Unlike common stock, preferred stockholders do not have voting rights and are paid a fixed dividend. Preferred stock is considered a type of equity investment and is not a money market instrument. Thus, the correct option is preferred stock.

preferred stock is not a money market instrument. What is a money market instrument A money market instrument is a debt security that matures in less than a year and is generally considered to be a low-risk investment because of its short-term nature and high liquidity. These securities are used by entities to manage short-term funding requirements. stock that pays dividends to shareholders. Unlike common stock, preferred stockholders do not have voting rights and are paid a fixed dividend. Preferred stock is considered a type of equity investment and is not a money market instrument. Thus, the correct option is preferred stock.

To know more about market instrument Visit:

https://brainly.com/question/5294223

#SPJ11

Company XYZ made no adjusting entry for accrued service revenue of $5.000 on December 31. No cash has been received from the customer yet. The entry to record the adjusting entry should have been: Debit Service Revenue $5,000 credit Accounts Receivable, $5,000 Debit Uneamed Revenue $5.000, credit Service Revenue: $5,000 O Debit Accounts Receivable $5.000, credit Service Revenue

Answers

The correct adjusting entry to record the accrued service revenue of $5,000 on December 31 should be:

Debit Accounts Receivable $5,000

Credit Service Revenue $5,000

An adjusting entry is necessary to recognize revenue that has been earned but not yet received in cash. In this case, the company provided services worth $5,000 for which no cash payment has been received by December 31. The revenue needs to be recognized in the financial statements even though the cash hasn't been received yet.

To record this adjusting entry, we debit Accounts Receivable to recognize the increase in the amount owed by the customer. The credit is made to Service Revenue, which increases the revenue account to reflect the earned revenue.

Accounts Receivable (Debit) $5,000

Service Revenue (Credit) $5,000

By recording the adjusting entry, the company properly recognizes the revenue it has earned, even though no cash has been received. This ensures accurate financial reporting and reflects the company's true financial position.

To know more about Accounts visit :

https://brainly.com/question/26690519

#SPJ11

If your speech is supposed to be 6-8 minutes long, which of the following durations should you aim for when timing and practicing your speech to ensure you are neither under time nor over time? Should you aim for 6:10, 8:00, 7:00, or none of the above?

Answers

Assuming that your speech should be 6-8 minutes in length, it would be ideal to hold back nothing that falls inside that reach. For this situation, you ought to go for the gold of 6:00 to 8:00 minutes.

Out of the choices you gave, the nearest range is 7:00 minutes. In the event that you go for the gold of around 7:00 minutes while timing and rehearsing your speech, you would have a decent possibility remaining inside the ideal time period of 6-8 minutes.

A speech is a conventional location or show given by a person to a crowd of people. It is a method for passing on data, sharing thoughts, offering viewpoints, or convincing audience members on a specific theme or issue.

Learn more about speech, from:

brainly.com/question/31881621

#SPJ4

Using relevant examples state and explain the major items sold
by marketing people.
Explain how the distribution channel for Unilever products can
be managed using the push and pull strategies.

Answers

Marketing people sell a wide range of items such as consumer goods, industrial goods, financial products, and digital products. The distribution channel for Unilever products can be managed through a combination of push strategies (direct distribution and sales promotion) and pull strategies (advertising and creating consumer demand).

Marketing people sell a wide range of items across various industries. Here are some examples of major items sold by marketing people:

1. Consumer Goods: Marketing people sell products like packaged food, beverages, personal care items, household products, and electronics. For example, marketing professionals promote and sell brands like Coca-Cola, Dove, iPhone, and Tide.

2. Industrial Goods: Marketing people also sell products and services to businesses and industries. Examples include heavy machinery, equipment, chemicals, software solutions, and consulting services.

For instance, marketing professionals sell industrial equipment from companies like Caterpillar or offer consulting services from firms like McKinsey & Company.

3. Financial Products: Marketing people play a crucial role in selling financial products such as insurance policies, mutual funds, investment portfolios, and banking services. They promote and sell offerings from companies like Prudential, Vanguard, and JPMorgan Chase.

4. Digital Products: With the rise of the digital age, marketing people sell various digital products and services. These include software applications, mobile apps, e-books, online courses, and digital subscriptions.

For example, marketing professionals promote and sell products like Microsoft Office 365, Udemy courses, and Netflix subscriptions.

The distribution channel for Unilever products can be managed using push and pull strategies. The push strategy involves pushing products through the distribution channel to reach the end consumers.

In this approach, Unilever can utilize its sales force to actively promote and distribute its products to retailers and wholesalers.

For example, Unilever sales representatives can visit retailers, offer incentives, and provide point-of-sale materials to encourage them to stock and sell Unilever products.

On the other hand, the pull strategy focuses on creating consumer demand, which then pulls the products through the distribution channel.

Unilever can implement this strategy by investing in advertising, public relations, and other marketing efforts to create brand awareness and drive consumer demand.

By effectively communicating the benefits and value of their products, Unilever can attract consumers to request and purchase their products from retailers, which then leads to increased orders from the retailers to Unilever.

By employing both push and pull strategies, Unilever can effectively manage its distribution channel.

The push strategy ensures availability of products in the market, while the pull strategy generates consumer demand, resulting in increased sales and market penetration for Unilever products.

To know more about distribution channel refer here:

https://brainly.com/question/20708885#

#SPJ11

Other Questions
9. One way for an auditor to document the intent of the governing board's decisions is to review and collect 10. There are two types of subsequent events of concern to the auditor. They include and 11 Suppose in his study, he collects sleep data from 31 adults and calculates the sample mean to be 6.78 hours and the sample standard deviation to be 0.23 hours. What can John conclude about his hypothesis? We can reject the null hypothesis, since the confidence interval does not contain 8 We cannot reject the null hypothesis, since the confidence interval does not contain 8 We can reject the null hypothesis, since the confidence interval contains 8 We cannot reject the null hypothesis, since the confidence interval contains 8 According to a longitudinal study, only one-third of adolescents followed from 6th to 10th grade showed ________________. F. Provide a screenshot of the completed project website(home/landing page only for the purpose of this assessment): calculate the stroke volume for a person with an edv of 170 ml, an esv of 90 ml, and a heart rate of 105 bpm. ____________ behavior attempts to satisfy the demands and concerns of both parties in a conflict situation. Suppose that the index model for stocks A and B is estimated from excess returns with the following results: RA 4.0%+0.50RM + eA RB 1.2 % + 0.70RM + e OM = 17%; R-square = 0.26; R-squareg = 0.18 A Please Find B and C. Garrison Oil, Inc. has an account titled Oil and Gas Properties, Garrison paid $6,000,000 for oil reserves holding an estimated 400,000 barrels of oil. Assume the company paid $520,000 for additional geological tests of the property and $460,000 to prepare for drilling. During the first year, Garrison removed and sold 85,000 barrels of oil. Record all of Garrison's transactions, including depletion for the first year. Record the payment for the oil reserves. Discussthe advantages and disadvantages of the application of technologyto human resource administrative processes and managementinformation requirements. Which of the following parts of a research project is always free of bias?A. identifying the projectB. selecting the sampleC. wording the questionsD. analyzing the dataCorrect AnswerE. none of the above The Lorean Group, an international holding company, recently acquired a controlling interest in Tiger Advertising. This advertising agency, which employees 6,644 people worldwide, has been successful since its inception in 1964. Revenues over the past four years have been flat, however, and costs of running the business have been climbing steadily. Tiger was acquired in spite of this recent decline in profits because of its reputation in the industry and its extended list of loyal clients. Lorean has a history of turning around troubled acquisitions, and the belief is that Tiger can be saved as well. survey research is a method of inquiry characterized by collecting data using structured questions to elicit self-reported information from a sample of people. a neurotransmitter (brain chemical) whose lack is associated with aggression is____. If a business inadvertently cashes such a check, the business has 90 days from the date it cashed that ch same amount to the debtor to avoid an accord and satisfaction. The business has no recourse, and the debt is deemed discharged and satisfied. If a business inadvertently cashes such a check, the business has 60 days from the date it cashed that che same amount to the debtor to avoid an accord and satisfaction. If a business inadvertently cashes such a check, the business has 30 days from the date it cashed that chec amount to the debtor to avoid an accord and satisfaction. If a business inadvertently cashes such a check, the business has 120 days from the date it cashed that chec same amount to the debtor to avoid an accord and satisfaction. 1. Discuss the importance of being proficient in the six core areas of human resources; staffing, human resource development, compensation and benefits, safety and health, employee and labor relations and performance management.2. Discuss the challenges of career planning given the statistic that college graduates will "face five to seven career changes3.Discuss the difference between direct and indirect compensation.4.Why is it important for HR to have an understanding of whats happening both in the "internal and external environment:"5.75% of our staff report that they found their job on the internet. Discuss the role of social media in recruiting6.Why is being a strategic player so important to the HR role?7.What are some of the ways that a countrys culture might impact the global role of HR?8. Do you think certification lends credibility to the HR profession? isten What era reflects a high attention to quality activities? Before the late 1970s From the mid 1990s to the present The Industrial Revolution Beginning in the late 1970s and continuing through the early 1990s arbitrage is a positive cash flow with no risk and none of thetrades own money invested? T or F Module 10. Raising Capital and Capital Structure 1. What is the order of capital? 2. Present the pros and the cons of each raising capital source. 3. How raising capital is related to the vision and the strategy of the business plan? 4. Why different kind of businesses require different strategy in raising capital? 5. What is crowdfunding? Analyze using the sources of capital prism. 6. Can you find examples of modern ways of raising capital? Analyze them. 7. What is the position of VC in the order of raising capital and why? 8. Does capital structure matter? How? 9. How cultural differences affect funding strategies? Examples. 10. You want to raise capital for a new VR game you and your colleague created. What will be your strategy? Why? X Find all points (x,y) on the graph of y = with tangent lines perpendicular to the line y = 3x - 1. x - 3 The point(s) is/are (Type an ordered pair. Use a comma to separate answers as needed.)